Shed Project 2016/17

IMG_20160730_07470512.jpg
July 30th 2016 - Look at the state of the shed... I know, I have an idea lets knock it down and build a new improved one - might take a couple of weeks (famous last words)!
IMG_20160730_07470713.jpg
July 30th 2016 - We might need to do some groundwork as it's a bit overgrown.
Shed 00514.jpg
September 10th 2016 - Cleared quite a lot and decided to replace the tatty broken fence (OK - might add a week to the job).
Shed 00915.jpg
September 10th 2016 - Time to get rid of the old shed.
Shed 01016.jpg
September 10th 2016 - Time to get rid of the old shed... nearly gone.
Shed 01217.jpg
September 10th 2016 - Time to get rid of the old shed... not much more.
Shed 01518.jpg
September 10th 2016 - Time to get rid of the old shed... what shed?
Shed 01619.jpg
September 10th 2016 - Ahhh, need to remove the old cherry tree stump to get the ground level.
Shed 01820.jpg
September 10th 2016 - Ahhh, need to remove the old cherry tree stump to get the ground level.
Shed 02621.jpg
September 10th 2016 - Start the way you plan to keep on... tidying up after you've cleared teh debris.
20160910_16412101.jpg
September 10th 2016 - Here is all the rubble which was removed by Lisa and Tony from the base of the old shed. Then taken to the tip in Tonys' car!
Shed 02722.jpg
September 11th 2016 - Lisa working hard levelling the ground under the old shed.
Shed 03923.jpg
September 11th 2016 - starting to look smarter in what was our piece of wasteground.
Shed 04624.jpg
September 17th 2016 - nearly built the base to support the new shed.
Shed 05525.jpg
September 24th 2016 - Building the walls from C24 tanalised 4x2 timbers.
Shed 05626.jpg
September 24th 2016 - Almost finished the supporting base and treated it to help preserve it.
Shed 06127.jpg
October 1st 2016 - Finished base in place and 38mm scaffold boards fitted for floor boards.
Shed 06728.jpg
October 8th 2016 - propped up a wall on the base to get an idea of what it will look like.
Shed 07229.jpg
October 22nd 2016 - Assembling and checking roof trusses for size on the base before erecting walls.
DSC_546511.jpg
October 15th 2016 - Building roof trusses in the rain, under a tarpaulin.
Shed 07630.jpg
October 30th 2016 - Lisa holding a roof truss in place to get an idea of what it will look like.
Shed 08331.jpg
November 7th 2016 - Walls are up just as the rain is coming down!
Shed 08732.jpg
November 19th 2016 - Tyvek Housewrap is pretty much in place - looking at the weather its a shame we dont have a roof!
Shed 08933.jpg
November 19th 2016 - OK that's enough - tried to get tarpaulin to protect what wasnt covered by Tyvek.
20161204-12131702.jpg
December 4th 2016 - Tony on the roof fixing the felt and battens.
20170114-10405403.jpg
January 14th 2017 - Starting to look like a building with the first window installed.
20170114-15505104.jpg
January 14th 2017 - Doors are fitted!
20170114-17220105.jpg
14th January 2017 - Burning the midnight oil to get on with it.
20170121-11201006.jpg
January 21st 2017 - Now comes the fun, I think! Starting to fit the 28mm larch cladding.
20170121-13204007.jpg
January 21st 2017 - started under the front window.
20170121-14210308.jpg
January 21st 2017 - A bit further on the front.
20170121-16295509.jpg
January 21st 2017 - Nearly finished the front wall.
20170122-16301910.jpg
January 21st 2017 - Front wall done up to the roof plate.
20170129-13331301.jpg
January 29th 2017 - Side wall with windows finished!
20170221_22115301.jpg
February 21st 2017 - This is what the insides look like now even though the roof hasnt been tiled yet!
20170221_22124203.jpg
February 21st 2017 - This is what the insides look like now even though the roof hasnt been tiled yet!
20170221_22125604.jpg
February 21st 2017 - This is what the insides look like now even though the roof hasnt been tiled yet!
20170221_22133605.jpg
February 21st 2017 - This is what the insides look like now even though the roof hasnt been tiled yet!
20170221_22120602.jpg
February 21st 2017 - This is what the insides look like now even though the roof hasnt been tiled yet!
20170221_22141106.jpg
February 21st 2017 - This is what the insides look like now even though the roof hasnt been tiled yet!
20170221_22143707.jpg
February 21st 2017 - This is what the insides look like now even though the roof hasnt been tiled yet!
20170225_16404801.jpg
February 25th 2017 - Fitted the sofit boards, so starting to look like a building now!
20170309_08001002.jpg
March 9th 2017 - Slate roof is started as you can see on the left side of the roof (view from rear bedroom window)
20170311_17411103.jpg
11th March 2017 - Slate roof is on and this is what it looks like from the neighbours garden.
20170401_10385804.jpg
1st April 2017 - during fitting the ventilate ridge tile system today.
20170401_11181005.jpg
1st April 2017 - finished fitting the ventilate ridge tile system today.
20170401_19303206.jpg
April 1st 2017 - This is what it looks like nested in the Magnolia tree!
20170422_15371207.jpg
April 22nd 2017 - Started fitted the Celotex wall insulation - who knew how bloody expensive this stuff is!!
20170509_18175202.jpg
2017-05-09 - Getting fed up with Celotex.
20170509_18180003.jpg
2017-05-09 Celotex fitted to walls
20170521_14395016.jpg
2017-05-21 - started fitting fireproof plasterboard... yes, pink is the new blue!!
20170525_07534820.jpg
2017-05-25 - More fireproof plasterboard being fitted.
20170527_18310425.jpg
2017-05-27 - Trench ready to take power, water and network!
20170527_19215929.jpg
2017-05-27 - 10mm armoured power cable lying in trench.
20170528_08591832.jpg
2017-05-28 - Aerial view of the utilities trench
20170528_15175933.jpg
20
20170529_11000734.jpg
2017-05-29 - polypipe and power feed inside shed
20170604_18260739.jpg
2017-04-06 - 24m of cable ducting left over!
20170610_20405644.jpg
2017-06-10 - starting to install floor insulation
20170610_20421046.jpg
2017-06-10 - starting to install floor insulation
20170613_21422648.jpg
2017-06-13 - OSB boards fitted on top of newly installed insulation
20170613_21431551.jpg
2017-06-13 - OSB boards fitted on top of newly installed insulation
20170613_21432452.jpg
2017-06-13 - OSB boards fitted on top of newly installed insulation
20170702-17244301.jpg
2nd July 2017 - Finished the pasterboarding.
20170702-17253902.jpg
2nd July 2017 - Finished the pasterboarding.
20170706-08024903.jpg
6th July 2017 - Plastering is complete
20170706-08030104.jpg
6th July 2017 - Plastering is complete
20170708-17412005.jpg
8th July 2017 - making and fitting the architraves
20170708-19504206.jpg
8th July 2017 - making and fitting the architraves
20170722-17112607.jpg
22nd July 2017 - Painting architraves
20170726-19392208.jpg
26th July 2017 - Painting walls and ceiling
20170726-20284009.jpg
26th July 2017 - Painting walls and ceiling
20170812-18083910.jpg
12th August 2017 - tackifier going on the newly laid hardboard
20170812-22575511.jpg
12th August 2017 - Laying the carpet tiles
20170813-19564312.jpg
13th August 2017 - newly laid carpet 🙂
20170813-19565913.jpg
13th August 2017 - newly laid carpet 🙂
20170813-19575214.jpg
13th August 2017 - newly laid carpet 🙂
20170815-23050715.jpg
15th August 2017 - Looks more like an office now with pictures, desk and everything!!